Site work |
ongoing |
|
|
|
Footings & Foundations |
4 weeks |
3/27/2006 |
4/23/2006 |
|
Fill for Slab |
1 week |
4/24/2006 |
4/30/2006 |
|
Underground Plumbing & Electrical |
3 weeks |
4/10/2006 |
5/7/2006 |
|
Start Metal Framing |
ongoing |
5/22/2006 |
|
|
Start Masonry |
ongoing |
4/24/2006 |
|
|
Start Structural Steel |
2 weeks |
4/10/2006 |
4/23/2006 |
|
Set Trusses for Addition |
3 weeks |
5/29/2006 |
6/18/2006 |
|
Start Metal Deck at Addition |
1 week |
6/19/2006 |
6/26/2006 |
|
Start Roofing |
ongoing |
6/26/2006 |
|
|
Start Plumbing & Electrical Rough In |
3 weeks |
6/23/2006 |
7/2/2006 |
|
Start Duct Work |
2 weeks |
6/26/2006 |
7/9/2006 |
|
Start Hanging Drywall |
4 weeks |
6/26/2006 |
7/23/3006 |
|
Start Ceiling Grid |
4 weeks |
7/24/2006 |
8/20/2006 |
|
Start Demo of Existing Bldg |
5 weeks |
6/12/2006 |
7/16/2006 |
|
Set Trusses on existing Bldg |
4 weeks |
6/19/2006 |
7/16/2006 |
|
Start Interior Framing in Existing Bldg |
3 weeks |
7/17/2006 |
8/6/2006 |
|
Start Plumbing & Electrical Rough Ins in Existing
Bldg |
3 weeks |
7/31/2006 |
8/20/2006 |
|
Start Hanging Drywall % Ceiling in existing Bldg |
5 weeks |
7/31/2006 |
9/3/2006 |
|
Interior Painting |
4 weeks |
9/4/2006 |
10/1/2006 |
|
Start Ceramic Tile |
2 weeks |
9/11/2006 |
9/24/2006 |
|
Install Plumbing Fixtures |
2 weeks |
9/18/2006 |
10/1/2006 |
|
HVAC |
ongoing |
|
|
|
VCT & Carpet for new & Existing |
5 weeks |
10/2/2006 |
11/6/2006 |
|
Aluminum Storefront, Glass Glazing |
ongoing |
|
|
|
Exterior Concrete Work Sidewalks & Curbs |
4 weeks |
7/10/2006 |
8/6/2006 |
|
Install Handrails & Ballards |
2 weeks |
8/7/2006 |
8/20/2006 |
|
Interior Doors & Hardware Toilet Partitions &
Accessories |
|
|
|
|
Exterior Signage |
|
|
|
|
Retaining Wall |
|
|
|